section 57
Execution of works in final scheme or local area plan by appropriate authority
The Mizoram Urban and Regional Development Act, 2025General2025105 sections13 chapters
Chapter IX IMPLEMENTATION OF TOWN PLANNING SCHEME AND LOCAL AREA PLAN
Statutory text
- (1) The Appropriate Authority shall complete all the works provided in a Final Scheme within the period specified in the Final Scheme. Provided that, on the request of the Appropriate Authority, the State Government may by an order in writing extend the period or periods.
- (2) If the Appropriate Authority fails to complete all the works within the specified period or within the period extended under sub-section (1), the State Government may, notwithstanding anything contained in sub-section (1), require the Appropriate Authority to complete the works within such further period as it may consider reasonable or appoint an officer or to any other authority to complete such works at the cost of the Appropriate Authority and recover the cost from the Appropriate Authority.
Study data processing for this section.
PDF: pending for this language.