section 30. Power of revocation and modification of permission for development.-
Power of revocation and modification of permission for development
The Bikaner Development Authority Act, 2025General2025116 sections
Statutory text
- (1) If it appears to the Authority that it is expedient, having regard to the Plan prepared or under preparation, that any permission to develop land granted under this Act or any other law should be revoked or modified, the Authority may after giving the person concerned an opportunity of being heard against such revocation or modification, by order, revoke or modify the permission to such extent as appears to it to be necessary: Provided that -
- (a) where the development relates to the carrying out of any building or other operation, no such order shall affect such of the operations as have been previously carried out or shall be passed after these operations have substantially progressed or have been completed;
- (b) where the development relates to a change of use of land, no such order shall be passed at any time after the change has taken place: Provided further that where the revocation or modification of the permission is necessary in public interest, the provisions of the first proviso shall not apply.
- (2) Where permission is revoked or modified by an order made under sub-section (1)