Execution of Works in the Area Development Scheme by Developer
The Bihar Urban Planning and Development Act, 2012Infrastructure2012113 sections14 chapters
Chapter VII AREA DEVELOPMENT SCHEME
Statutory text
Execution of Works in the Area Development Scheme by Developer.-
- (1) The developer shall complete all the works provided in an Area Development Scheme within the period prescribed; Provided that, in exceptional circumstances on application by the developer, the Planning Authority may, by an order in writing specifying these circumstances, grant to the developer in this behalf, further extension of time as it may think fit.
- (2) If the developer fails to complete the work within the prescribed period or within the period extended under sub-section (1), the Planning Authority may, notwithstanding anything contained in sub-section (1), require the developer to complete the works within a further period as it may consider reasonable or appoint other agency/agencies to complete such works at the cost of the developer and may imposed such penalties on the developer as prescribed.
Study data processing for this section.
PDF: pending for this language.