section 19
Statement of liability
The Orissa Soil Conservation Act, 1965Environmental196531 sections5 chapters
Chapter III EXECUTION OF SCHEMES AND MAINTENANCE AND REPAIR OF WORKS
Statutory text
- (1) For purposes of section 18 the Collector shall prepare a draft statement giving for any specified area the following particulars, namely: -
- (a) the work done;
- (b) a map showing the work done;
- (c) the cost of such work;
- (d) the persons who in the opinion of the Collector are liable jointly or severally to maintain and repair any such work; and
- (e) such other matters as may be prescribed.
- (2) The draft statement prepared under sub-section
- (1) shall be published in the prescribed manner inviting objections from the persons affected to be submitted to the Collector within thirty days from the date of such publication.
- (3) The Collector shall consider all such objections as are received under sub-section
- (2) and after holding such enquiry as he deems fit and giving the persons filing such objections an opportunity of being heard, by order confirm the statement with such alterations or modifications, if any, as he deems fit and proper.
- (4) Any person aggrieved by an order under sub-section
- (3) in respect of any entry in the statement may, before the expiry of thirty days from the date of such order, appeal to the State Government in the manner prescribed and the orders of the State Government passed in such appeal shall be final.
- (5) The statement prepared in accordance with the foregoing sub-sections may, on the application of any person interested, be revised by the Collector by an order made by him in that behalf in the prescribed manner on the ground of any change in the beneficiaries shown in such statement and all such orders shall have effect subject to the decision in an appeal, if any, so far as may be in accordance with sub-section (4).