Realisation of costs
The Orissa Soil Conservation Act, 1965Environmental196531 sections5 chapters
Chapter III EXECUTION OF SCHEMES AND MAINTENANCE AND REPAIR OF WORKS
Statutory text
- (1) On the execution of any scheme under this Act the State Government shall, having regard to-
- (a) the amount of costs incurred in the execution of such scheme;
- (b) the nature and scope of the scheme;
- (c) the economic conditions of the beneficiaries; and
- (d) any other factor as the State Government may consider relevant in that behalf, by notified order giving reasons therefor, specify whether or not the whole or any part of the aforesaid costs may be recovered from the beneficiaries or any section thereof and the amount, if any, that may be so recovered and thereupon the Collector shall recover the said amount from such beneficiaries in such proportion and in such instalments as he may, by order, determine: Provided that the Collector in apportioning the costs amongst such beneficiaries shall have regard to the extent of the benefits conferred by the scheme.
- (2) Any person aggrieved by an order passed by the collector under sub-section
- (1) may, before the expiry of thirty days from the date of such order, appeal to the State Government in the prescribed manner and the orders of the State Government passed in such appeal shall be final.