- (1) If, after considering any objections or suggestions, which may have been made in respect to the draft before the expiry of the period specified in sub-section
- (2) of section 29, the Licensing Authority is of the opinion that the application should be granted with or without modifications, or subject to any restrictions or conditions, it shall grant a licence accordingly.
- (2) The Promoter can undertake all preparatory activities including tendering and onboarding of contractors but shall have to obtain a licence under this section before the commencement of construction.
- (3) Every licence authorising the construction of a ropeway granted under sub-section
- (1) shall, in such from as may be prescribed, be uploaded on the website of the State Government.