section 14
Provisional declaration of affected zone and benefited zone
The Maharashtra Resettlement of Project Displaced Persons Act, 1976General197632 sections
Statutory text
- (1) As soon as may be after the receipt of the copy of the assessment under section 13, the State Government shall, after such inquiry as it thinks fit, provisionally declare by notification in the Official Gazette and also in the manner provided by sub-section
- (2) of section 11—
- (a) the area which is required for the Project, and thereby would be adversely affected by or under the Project; and
- (b) if the Project is an irrigation Project or is a composite Project consisting of irrigation Project, power Project and any other Project of public utility or any combination thereof the area under the command of the Project which is likely to be benefited by the Project.
- (2) The declaration under sub-section
- (1) shall invite objections to, and suggestions for, the inclusion of any land in the area referred to in clause
- (a) or clause
- (b) of sub-section
- (1) within a period of not less than thirty days specified in the notification.
- (3) A copy of the notification shall be sent to the Commissioner, the Deputy Director and the Resettlement Officer who may make such suggestions relating to the notification as he thinks fit.