Water Budgeting at Project Level.
The Maharashtra Management of Irrigation Systems by Farmers Act, 2005Infrastructure200581 sections8 chapters
Chapter VIII GENERAL PROVISIONS
Statutory text
- (1) Water budgeting, that is to say, preparing the preliminary Irrigation programme for the project, in consultation with the Canal Officer duly empowered in this behalf, shall be the responsibility of the Project Level Association. Such Preliminary Irrigation Programme shall be based on priorities determined by the State Government, from time to time. Explanation.-When a Project Level Association does not exist, the preparation of preliminary Irrigation programme shall be the responsibility of the concerned Canal Officer.
- (2) The Applicable Water Use Entitlement shall be worked out every year or, every season as the case may be, considering practical situation and directives issued by the State Government.
Study data processing for this section.
PDF: pending for this language.