- (1) In case the public infrastructure agency considers that it is necessary to terminate any concession, it may terminate the same strictly in accordance with the provisions of the Concession Agreement signed between the parties by passing a speaking order in this behalf, after affording reasonable opportunity of being heard, to such concessionaire. If such concessionaire feels aggrieved of any such termination order, he may file an appeal before the Authority, in this behalf stating the reasons, for setting aside of such order43.
- (2) Where a Concession Agreement is terminated by the public infrastructure agency with or without the consent of the concessionaire, the concessionaire shall be entitled to such amount of compensation for such termination, as is specified in the Concession Agreement.
Study data processing for this section.
Some statutory text is still being prepared for this language version.
PDF: pending for this language.