section 2
Insertion of new section
The Electricity (Supply) (Punjab Amendment) Act, 1959Insertion of new section 27-A in Central Act LIV of 1948.—After section 27 of the Electricity (Supply) Act, 1948 in its application to the State of Punjab (hereinafter referred to as the principal Act) the following section shall be inserted, namely:— "27A. Transfer of electrical works of Bhakra-Nangal Project to Board.—Notwithstanding anything contained in this Act, the [Government of Himachal Pradesh] hereinafter referred to as the 'State Government') may transfer to the Board, for the purpose of this Act, its rights and interests relating to the management and control of the electrical portion of the Bhakra-Nangal Project and all works connected therewith, including common pool works and works, if any, undertaken by the State Government on behalf of the Government of Rajasthan, that the Board shall assume the control and management of such rights and interests subject to the terms of any agreement relating to common pool works as may have been or may be executed in that behalf by the State Government with the Government of Rajasthan. Explanation.—For the purposes of this section the expression 'common pool works' shall mean the following works:—
- (i) Bhakra Power-house including the step-up sub-station.
- (ii) Nangal Power-houses at Ganguwal and Kotla including the step-up sub-stations at these place.
- (iii) Double circuit 132 KV Transmission Line between Ganguwal Power-house and Ludhiana including the Grid sub-station at Ludhiana.
- (iv) 132/220 KV Transmission Line between Bhakra and Delhi, and the connected Grid sub-stations at Dhulkote (Ambala), Panipat and Delhi.
- (v) Single Circuit 132 KV Transmission line between Ludhiana and Jullundur including the connected Grid sub-stations at Jullundur.
- (vi) Single Circuit 132 KV Transmision line between Ludhiana and Muktsar including the connected Grid sub-stations at Moga and Muktsar.
- (vii) Single Circuit 132 KV Transmission Line between Panipat and Hissar including the connected Grid sub-stations at Hansi and Hissar.
- (viii) The circuit 66 KV Transmission line from Bhakra Power-house to the Nangal Fertilizer Factory."