section 9
Repeal and saving
The Punjab-One-Time-Voluntary-Disclosure-and-Settlement-of-Violations-of-the-Buildings-Constructed-in-Violation of the Building Bye-laws in the Corporations and the Municipalities Act, 2004(1) The Punjab one-time Voluntary Disclosure and Set- tlement of Violations of the Buildings constructed in violation of the Building Bye-laws in the Corporations and the Municipalities Ordinance, 2004 (Punjab Ordinance No. 1 of 2004), is hereby repealed. (2) Notwithstanding such repeal, anything done or action taken under the Ordinance referred to in sub-section (1), shall be deemed to have been done or taken under the corresponding provisions of this Act. Forms Form ‘A’ [See sections 3 and 6(2)] Application form for settlement of non-compoundable violations To The Commissioner/Executive Officer, Municipal Corporation/Municipal Council/Nagar Panchayat, --------------------. Sir, I/We have constructed a building which is in violation of the provisions of the Punjab Municipal Corporation Act, 1976/the Punjab Municipal Act, 1911 or the Building Bye-laws framed thereunder and which is a non-compoundable violation under the Punjab one-time Voluntary Disclosure and Settlement of Violations of the Buildings constructed in Violation of the Building Bye-laws in the Corporation and the Municipalities Act, 2004. The particulars of the said building are as under :- (a) Name and address of the Owner of the Building : (b) Description of the Building : (c) Total plot area : (d) Date(s) and Year(s) of construction; (e) Total covered area to be regularized floor-wise: (i) Basement ______________________ sft. (ii) Ground floor ______________________ sft. (iii) First floor ______________________ sft. (iv) Second floor _____________________ sft. (f) Rates of compromise fee applicable; and Rs.________________ per sft. (g) Total amount of composition fee Rs. ____________________. (Indicate Bank draft No.---------------------- Date--------------). 2. I/we hereby request that the said building may be considered for regulariza- tion in terms of the provisions of the Punjab One-time Voluntary Disclosure and Punjab One-Time Voluntary Disclosure ...Municipalities Act, 2004, 5 Settlement of Violations of the Buildings constructed in Violation of the Building Bye-laws in the Corporations and the Municipalities Act, 2004. 3. I/we declare that no Government or Municipal or public land, including road/street has been encroached upon in the construction of the building. 4. I/we undertake and declare that the building constructed or any portion thereof, does not constitute any threat to the public safety. 5. I/we also undertake to abide by and comply with all the conditions, which may be imposed while regularizing the aforesaid unauthorized building. 6. I/we solemnly affirm and declare that the above information is true and cor- rect to the best of my/our knowledge and belief and the amount of composition fee deposited will be without prejudice to the final order/decision of the competent authority. 7. The following documents are enclosed herewith :- (a) Copy of ownership of document; (b) Copy of approved building plan, if any; (c) Plan of all the floors showing existing construction and arrangement of water supply and disposal of sewage; (d) Elevation and Typical X-Section of the building; (e) Structural Safety Certificate given by the recognized Structural Engineer; and (f) Fire Safety Certificate. --------------
- (2) Notwithstanding such repeal, anything done or action taken under the Ordinance referred to in sub-section (1), shall be deemed to have been done or taken under the corresponding provisions of this Act. Forms Form ‘A’ [See sections 3 and 6(2)] Application form for settlement of non-compoundable violations To The Commissioner/Executive Officer, Municipal Corporation/Municipal Council/Nagar Panchayat, --------------------. Sir, I/We have constructed a building which is in violation of the provisions of the Punjab Municipal Corporation Act, 1976/the Punjab Municipal Act, 1911 or the Building Bye-laws framed thereunder and which is a non-compoundable violation under the Punjab one-time Voluntary Disclosure and Settlement of Violations of the Buildings constructed in Violation of the Building Bye-laws in the Corporation and the Municipalities Act, 2004. The particulars of the said building are as under :-
- (a) Name and address of the Owner of the Building :
- (b) Description of the Building :
- (c) Total plot area :
- (d) Date(s) and Year(s) of construction;
- (e) Total covered area to be regularized floor-wise:
- (i) Basement ______________________ sft.
- (ii) Ground floor ______________________ sft.
- (iii) First floor ______________________ sft.
- (iv) Second floor _____________________ sft.
- (f) Rates of compromise fee applicable; and Rs.________________ per sft.
- (g) Total amount of composition fee Rs. ____________________. (Indicate Bank draft No.---------------------- Date--------------). 2. I/we hereby request that the said building may be considered for regulariza- tion in terms of the provisions of the Punjab One-time Voluntary Disclosure and Punjab One-Time Voluntary Disclosure ...Municipalities Act, 2004, 5 Settlement of Violations of the Buildings constructed in Violation of the Building Bye-laws in the Corporations and the Municipalities Act, 2004. 3. I/we declare that no Government or Municipal or public land, including road/street has been encroached upon in the construction of the building. 4. I/we undertake and declare that the building constructed or any portion thereof, does not constitute any threat to the public safety. 5. I/we also undertake to abide by and comply with all the conditions, which may be imposed while regularizing the aforesaid unauthorized building. 6. I/we solemnly affirm and declare that the above information is true and cor- rect to the best of my/our knowledge and belief and the amount of composition fee deposited will be without prejudice to the final order/decision of the competent authority. 7. The following documents are enclosed herewith :-
- (a) Copy of ownership of document;
- (b) Copy of approved building plan, if any;
- (c) Plan of all the floors showing existing construction and arrangement of water supply and disposal of sewage;
- (d) Elevation and Typical X-Section of the building;
- (e) Structural Safety Certificate given by the recognized Structural Engineer; and
- (f) Fire Safety Certificate. --------------
Study data processing for this section.