section 8
Cessation of powers given by an order.
The Punjab Aerial Ropeways Act, 1926General192637 sections
Statutory text
If a promoter authorized by an order to construct an aerial ropeway does not, within the time specified in the order, (a) succeed in raising the full amount of capital required for the completion of the aerial ropeway; (b) make, in the opinion of the Central Government, substantial progress with the construction of the aerial ropeway; or (c) complete the construction thereof; the powers given to the promoter by such order shall, unless the Central Government prolongs the time so specified, cease to be exercised.