section 7
Grounds of rejection of proposal.
The Maharashtra Infrastructure Development Enabling Authority Act, 2018Infrastructure201828 sections4 chapters
Chapter III INFRASTRUCTURE PROJECTS DELIVERY PROCESS
Statutory text
The Authority may reject the proposal if,-
- (i) such proposal does not fulfil the eligibility criteria provided under section 13; or
- (ii) such Person fails to furnish the appropriate information or documents or the clarifications sought by the Authority, within the time communicated to it; or
- (iii) the information or documents submitted by such Person are not in accordance with the prescribed Forms; or
- (iv) the contents or information or documents submitted are incomplete or deficient or found to be false; or
- (v) the Person has failed to make payment of the fees in the manner as may be prescribed; or
- (vi) any other grounds as may be prescribed.