The Gujarat Special Investment Region Act, 2009
Chapter IX REDRESSAL OF GRIEVANCES AND SETTLEMENT OF
Chapter IX REDRESSAL OF GRIEVANCES AND SETTLEMENT OF
25. Redressal of Grievances and Disputes Resolution Forum
Without prejudice to the jurisdiction of any court of law, and to the provisions of the Arbitration and Conciliation Act, 1996, an internal Disputes Settlement Mechanism for the purposes of this Act shall be as follows, namely:- (1) The Regional Development Authority shall set up a Grievances Redressal Committee comprising of such number of its members and officers, as may be decided by it to redress the grievances and resolve the disputes originating from any stakeholder in the Special Investment Region. (2) Any person aggrieved by the decision of Grievances Redressal Committee may appeal to the Disputes Resolution Forum set up by the Apex Authority comprising of such number of members and officers as may be decided by it. (3) For the purpose of deciding the disputes, the Grievances Redressal Committee and the Disputes Resolution Forum shall frame the guidelines including the time frame in this regard and follow the principles of natural justice while dealing with the grievances.
Chapter IX REDRESSAL OF GRIEVANCES AND SETTLEMENT OF
26. Disputes Settlement Mechanism
(1) The State Government may, by notification in the Official Gazette, form a Disputes Settlement Mechanism consisting of such number of members as may be specified by it, to deal with the disputes against Regional Development Authority or those arising in any manner in the Special Investment Region and brought before it or those which could not be resolved or settled by the Grievances Redressal Committee and the Disputes Resolution Forum. (2) The qualification, tenure of office and other terms and conditions of the Chairperson and members of the Disputes Settlement Mechanism shall be such as may be prescribed by rules. (3) For the purpose of deciding the disputes, the Disputes Settlement Mechanism shall frame the guidelines including the time frame in this regard and follow the principles of natural justice while dealing with the disputes. (4) The order passed by the Disputes Settlement Mechanism shall be final.
PDF: pending for this language.