The Bihar Regional Development Authority Act, 1974In cases where a builder seeks permission to resume construction and produces before the Vice-Chairman, PROA, the sanctioned plan, on prima facie satisfaction the PROA may permit him to continue with the construction subject to the ultimate result after verification of the building plan and actual construction work-if on final verification of the sanctioned plan and the actual construction work done, deviation is found the builder shall not object to the demolition of such structure on the mere ground that he was allowed to raise the construction provisionally-In cases of compoundable deviation the PADA may exercise its discretion but in cases where the deviation is not compoundable, the PROA will direct the builder to remove such construction.