184. Notice of construction of building
Notice of construction of building. (1) The expression “to construct a building” throughout this Chapter includes— (a) any material alteration, enlargement or reconstruction of any building, or of any wall including compound wall and fencing, verandah, fixed platform, plinth, door step or the like, whether constituting part of a building or not; (b) the conversion into a place for human habitation of any building not originally constructed for human habitation; (c) the conversion into more than one place for human habitation of any place originally constructed as one such place; (d) the conversion of two or more places of human habitation into a greater number of such places; (e) such alterations of the internal arrangements of a building, as affect its drainage, ventilation or other sanitary arrangements, or its security or stability; and (f) the addition of any rooms, buildings, or other structures to any buildings, and a building so altered, enlarged, reconstructed, converted or added to, is throughout this Chapter included under the expression “a new building”. (2) Before beginning to construct any building, the person intending so to construct shall give to the Chief Officer notice thereof in writing and shall furnish to him at the same time, if required by a bye-law or by a special order to do so, a plan showing the levels, at which the foundation and lowest floor of such building are proposed to be laid, by reference to some level known to the Chief Officer, and all information required by the bye-laws or demanded by the Chief Officer regarding the limits, design, ventilation and materials of the proposed building, and the intended situation and construction of the drains, privies, water-closets, house-gullies and cess-pools, if any, to be used in connection therewith, and the location of the building with reference to any existing or projected streets, the means of access to such building and the purpose for which the building will be used: Provided that, if the bye-laws of the Council so require, such notice shall be in such form as the Council may from time to time prescribe and such plans shall be signed by a person possessing the qualifications laid down in the bye-laws or licensed under the bye-laws so to sign such plans. (3) If the person giving notice under sub-section (2) fails to— (i) furnish all the information and documents required under sub-section (2); or (ii) the Chief Officer deems it necessary to call for any further information or documents, the Chief Officer shall, within sixty days of the receipt of the notice, require such person by an order in writing to furnish such information or documents. (4) Within sixty days of the receipt by the Chief Officer of the notice under sub-section (2), or if any further information and documents have been called for under sub-section (3) then within sixty days of the receipt of all such further information and documents, the Chief Officer may— (a) grant the necessary permission to construct according to the plans and information furnished under sub-section (2) and sub-section (3); (b) impose any conditions in accordance with this Act or the rules and bye-laws made thereunder, as to the level, drainage, sanitation, materials or to the number of storeys to be erected, or with reference to the location of the building in relation to any street existing or projected or to the means of access to such building on the purpose for which the building is to be used; (c) direct that the work shall not be proceeded with unless and until all questions connected with the respective location of the building or street have been decided to his satisfaction; (d) subject to the provisions of the next succeeding section, refuse such permission for reasons which shall be communicated to the applicant in writing. (5) The Council may, before any work has been commenced in pursuance of any permission granted by the Chief Officer under sub-section (4), revoke such permission and may give fresh permission in lieu thereof or issue any other order as may be passed by the Chief Officer under sub-section (4). (6) If the Chief Officer fails to issue an order under clause (c) or (d) of sub-section (4) within the period prescribed in that sub-section, the person giving notice under sub-section (2) shall, after the expiry of the said period, be entitled to proceed with the work in respect of which such notice has been given under sub-section (2), in the manner specified in such notice, provided that such manner is not inconsistent with any provision of this Act or any rule or bye-law for the time being in force thereunder. (7) No person who becomes entitled under sub-section (4), (5) or (6) to proceed with any intended work of which notice is required by sub-section (2), shall commence such work after the expiry of the period of one year from the date on which he first became entitled so to proceed therewith, unless he shall have again become so entitled by a fresh compliance with the provisions of sub-sections (2) to (6). (8) If any person begins any construction of a building of which notice is required to be given under sub-section (2)— (i) without the permission of the Chief Officer under sub-section (4) or of the Council under sub-section (5), save as otherwise provided under sub-section (6); or (ii) having received permission under clause (a) of sub-section (4), contrary to the plans and information furnished under sub-sections (2) and (3); or (iii) having received permission under clause (b) of sub-section (4), contrary to the conditions imposed under that clause or contrary to the plans and information submitted under sub-sections (2) and (3) in so far as such plans and information are not modified by such conditions; or (iv) contrary to the provisions of sub-section (6), when construction is begun under that sub-section, the Chief Officer may, by a written notice, require such person to stop such construction and to alter or demolish any construction already made as specified in the notice. If, within fifteen days from the service of such notice for demolishing any such construction, the work of demolishing it is not commenced, the Chief Officer may cause such work to be done and the expenses incurred therefor shall be recoverable from the person concerned in the same manner as an amount due on account of a property tax. (9) Any person who fails to comply with the notice issued by the Chief Officer under sub-section (8), shall, on conviction, be punished with fine which may extend to fifteen thousand rupees. (10) The Court convicting such person may also direct such person to demolish or alter the building in accordance with the order of the Chief Officer or in such other manner as the Court may deem proper and within the period specified by the Court. If such person fails to demolish or alter the building within the period specified by the Court, or in the manner required by the Court, he shall, on conviction, be punished with further fine which may extend to one hundred rupees for every day after the expiry of the period for compliance specified by the Court in its order during which such non-compliance continues. (11) Nothing in sub-section (8) or (10) shall be deemed to affect the power of the Council or the Chief Officer to demolish or alter the building under section 190. (12) The Chief Officer may, at any time, inspect without giving notice of his intention to do so, any work of which notice is required by sub-section (2); and at any time during the execution of any work may, by written notice, specify any matter in respect of which the execution of such work is in contravention of any provision of this Act or of any bye-laws made under this Act or of any order passed under this section; and require the person executing such work to cause anything done contrary to any such provision or bye-laws or order to be amended or to do anything which by any such provision or bye-law or order he is required to do but which has been omitted. (13) Any person aggrieved by an order of the Chief Officer made under sub-section (8) may prefer an appeal against the order to the Appellate Tribunal within the period specified in the order for the demolition of the construction or work to which it relates. (14) Where an appeal is preferred under sub-section (13) against the order of demolition, the appellate Tribunal may, subject to the provisions of sub-section (3) of section 184 C, stay the enforcement of that order on such terms, and for such purpose, as it may think fit: Provided that where the erection of any building or execution of any work has not been completed at the time of the making of the order of demolition, no order staying the enforcement of the order of demolition shall be made by the Appellate Tribunal unless security sufficient in the opinion of the said Appellate Tribunal has been given by the appellant for not proceeding with such erection or work pending the disposal of the appeal. (15) Subject to any order may by the Government on appeal under section 184 D, every order made by the Appellate Tribunal on appeal under this section, and subject to the orders of the Government and the Appellate Tribunal on appeal, the order of demolition made by the Chief Officer shall be final. (16) Where no appeal has been preferred against an order of demolition made by the Chief Officer under sub-section (8) or where an order of demolition made by the Chief Officer under that sub-section has been confirmed on appeal, whether with or without variation, by the Appellate Tribunal in a case where no appeal has been preferred against the order of the Appellate Tribunal, and by the Government in a case where an appeal has been preferred against the order of the Appellate Tribunal, the persons against whom the order has been made shall comply with the order within the period specified therein, or as the case may be, within the period, if any, fixed by the Appellate Tribunal or Government on appeal and on the failure of the person to comply with the order within such period, the Chief Officer may himself cause the erection or the work to which the order relates to be demolished and the expenses of such demolition shall be recoverable from such person as an amount due on account of property tax. (17) If an order made by the Chief Officer under sub-section (8) directing any person to stop the construction is not complied with, the Chief Officer may in addition to any other action that may be taken under this Act, may require any Police Officer to remove such person or his assistants and workmen from the premises or to seize any construction material, tool, machinery, scaffolding or other things used in the construction within such time as may be specified in the requisition and such Police Officer shall comply with the requisition accordingly. (18) Any of the things caused to be seized by the Chief Officer shall be disposed off by him in the manner specified in section 156. (19) After the requisition under sub-section (18) has been complied with, the Chief Officer may, if he thinks fit, depute by a written order, a Police Officer or a Municipal Officer or other Municipal employee to watch the premises in order to ensure that the construction is not continued. (20) Where a Police Officer or a Municipal Officer or other Municipal employee has been deputed under sub-section (19) to watch the premises, the cost of such deputation shall be paid by the person at whose instance such construction is being continued or to whom notice under sub-section (8) was given and shall be recoverable from such person as an amount due on account of a property tax. (21) Notwithstanding anything contained in any other provisions of this Act, the Chief Officer may, subject to the recommendation of the Council, regularize any construction in respect of which no notice as required under sub-section (2) has been given, on payment of a fine equivalent to the fees and taxes payable in respect thereof from the date of commencement of such construction, provided that such construction is as per the building bye-laws and complies with the provisions of any other law for the time being in force. (4) Subject to rules that may be made by the Government in this behalf, the awarding of damages in and the cost of, and incidental to, any appeal before an Appellate Tribunal, shall be in its discretion and it shall have full power to determine by and to whom, and to what extent and subject to what conditions, if any, such damages or costs are to be paid and to give, in its order disposing of an appeal, necessary directions for the purpose aforesaid. (5) An order of the Appellate Tribunal made under this section may be executed or caused to be executed by it on the application of the person in whose favour the order has been made. (6) In hearing and deciding an appeal or in the execution of an order, the Appellate Tribunal shall follow such procedure as may be prescribed by rules. (7) Every Appellate Tribunal shall, in addition to the powers conferred on it under this Act, have the same powers as are vested in a Civil Court while trying a suit under the Code of Civil Procedure, 1908 (Central Act 5 of 1908), in respect of the following matters, namely:— (a) Summoning and enforcing the attendance of persons and examining them on oath; (b) requiring the discovery and inspection of documents; (c) receiving evidence on affidavits; (d) requisitioning any public records or copies thereof from any court or office; (e) issuing commissions for the examination of witnesses or documents; and (f) any other matter which may be prescribed by rules, and every proceeding of an Appellate tribunal in hearing or deciding an appeal or in connection with the execution of its order, shall be deemed to be a judicial proceeding within the meaning of sections 193 and 228 and for the purpose of section 196 of the Indian Penal Code (Central Act 45 of 1860), and every Appellate Tribunal shall be deemed to be a Civil Court for the purpose of section 195 and Chapter XXVI of the Code of Criminal Procedure, 1973 (Central Act 2 of 1974).
Chapter XII Chapter XII
184A. Power to seal unauthorized constructions
(1) It shall be lawful for the Chief Officer, at any time, before or after making the order of demolition or of the stoppage of the construction under section 184, to make an order directing the sealing of the premises in which such construction is being carried on or has been completed for the purpose of carrying out the provisions of this Act, or for preventing any dispute as to the nature and extent of such constructions. (2) Where any premises in which any construction is being carried on has been sealed, the Chief Officer may, for the purpose of demolishing such construction in accordance with the provisions of this Act, order the seal to be removed. (3) No person shall remove such seal except— (a) Under an order made by the Chief Officer under sub-section (2); or (b) under an order of an Appellate Tribunal or the Government, made in appeal under this Act.
Chapter XII Chapter XII
184D. Appeal against order of Appellate Tribunal
(1) An appeal shall lie to the Government against an order of the Appellate Tribunal, made in an appeal under section 184 confirming, modifying or annulling an order made or notice issued under this Act. (2) The provisions of section 184 and the rules made there under, shall, so far as may be, apply to the filling and disposal of an appeal under that section. (3) An order of the Government on an appeal under this section, and subject only to such order, an order of the Appellate tribunal under section 184, and subject to such orders of the Government or an Appellate Tribunal, an order or notice referred to in that section, shall be final.
Chapter XII Chapter XII
184F. Preparation of development plan
Every Council shall prepare every year a development plan and submit it to the District Planning Committee constituted under section 239 of the Goa Panchayat Raj Act, 1994 ( Act 14 of 1994 ).
Chapter XII Chapter XII
185. Powers of Chief Officer and Council to refuse permission
(1) When a person has given notice to the Chief Officer under sub-section (2) of the last preceding section in regard to his intention to construct a building, it shall be lawful to the Chief Officer to refuse the permission applied for— (i) if the Council passes a resolution proposing to acquire the land on which the building is proposed to be constructed; or (ii) if the proposed construction would contravene the provisions of this Act, or any other law for the time being in force or any scheme, rules, bye-laws or other orders under this Act or any other law for the time being in force; or (iii) if the notice under sub-section (2) of the last preceding section is not in accordance with the provisions of that sub-section or is not accompanied by the information and documents required by that sub-section or if the person giving such notice fails to furnish all the information and documents required under sub-section (3) of that section; or (iv) if no plan has been prepared for the laying out of streets for the area in which the building is to be constructed; or (v) if there is no adequate provision for access to the building; or (vi) if the proposed construction be an encroachment on Government or municipal land; or (vii) for any other reasons to be recorded in writing, which may be deemed sufficient by the Chief Officer. Where the permission applied for its refused the decision taken and reasons therefor shall be communicated to the applicant. (2) Refusal under clause (i) of sub-section (1) shall be subject to the following conditions:— (a) if the property is acquired and no agreement is arrived at as regards the amount of compensation payable to the person giving notice under sub-section (2) of the last preceding section, the same shall be determined in accordance with the provisions of section 315 regard being had to the likely benefit, which would have accrued to such person, if the permission had not been refused; (b) if within a period of six months from the date of the resolution of the Council proposing to acquire the land, the land is not acquired by the Council by agreement upon payment, or if within such period, an application has not been made to the Collector for the institution of proceedings for compulsory acquisition under the provision of the Land Acquisition Act, 1894, or if the Council abandons the proposal to acquire the land, the notice given under sub-section (2) of the last preceding section shall be deemed to have been revived with effect from the date on which the said period of six months expires, or with effect from the date on which the decision of the Council to abandon the proposal is arrived at, as the case may be. Such decision shall be communicated to the person giving notice, within fifteen days from the date of the decision; and the notice shall be dealt with as if the Council had not passed a resolution to acquire the land. The Council shall be liable to pay compensation to the said person in respect of the loss which he may prove to have incurred by reason of the Council’s refusal to grant the permission: Provided that the Council shall not be liable to pay compensation if the notice under sub-section (2) of the last preceding section is given subsequent to the passing of the resolution by the Council to acquire the land.
Chapter XII Chapter XII
186. Level of buildings
Level of buildings. After the appointed day, no building shall be constructed upon a lower level than will allow of the drainage thereof being led into some public sewer or drain either then existing or projected by the Council or into some stream or river or into the sea or some cess-pool or other suitable place which may be approved of by the Chief Officer.
Chapter XII Chapter XII
187. Roofs and external walls of buildings not to be made of inflammable materials
(1) The external roofs and walls of buildings constructed or renewed after the appointed day, shall not be made of grass, wood, cloth, canvas, leaves, mats or other inflammable material, except with the written permission of the Chief Officer, which may be given either specially in individual cases, or generally in respect of any area specified therein. (2) The Council may by bye-laws prescribe— (i) the areas in which permission shall be granted by the Chief Officer for the construction of external roofs and walls of buildings from any inflammable material; (ii) the conditions which may be imposed by the Chief Officer in granting permission for such construction in any other area.
Chapter XII Chapter XII
188. Completion certificate, permission to occupy or use
Completion certificate, permission to occupy or use. (1) Every person constructing a building shall, within one month after the completion of construction of such building, deliver or send or cause to be delivered or sent to the Chief Officer at his office, notice in writing of such completion and shall give to the Chief Officer all necessary facilities for inspection of such building: Provided that— (a) such inspection shall be commenced with in seven days from the date of receipt or the notice of completion; and (b) the Chief Officer may, not later than one month from the date of receipt of the notice of completion, by written intimation addressed to the person from whom the notice of completion was received,— (i) give permission for the occupation of such building or for the use of the building or part thereof affected by such construction; or (ii) refuse such permission in case such building has been constructed so as to contravene any provision of this Act or of any bye-law made under this Act at the time in force or of any order passed under section 184 intimating to the person who gave the notice under sub-section (2) of that section, the reasons for such refusal and requiring such person, or if the person responsible for giving notice under sub-section (2) of the said section is not at the time of such notice owner of such building, then such owner to cause anything which is contrary to any provision of this Act or of any bye-law made under this Act at the time in force or of any order passed under section 184 to be amended or to do anything which by any such provision or bye-law or order he is required to do but which has been omitted. (2) No person shall occupy or permit to be occupied or use or permit to be used any such building constructed or part thereof affected by such construction, until— (a) the permission referred to in proviso (b) to sub-section (1) has been received, or (b) the Chief Officer has failed for one month after the receipt of the notice of completion to intimate as aforesaid his refusal of the said permission. (3) Whoever— (a) occupies or permits to be occupied any such building or part thereof affected by such construction without giving any notice as required under sub-section (1) or in contravention of the provisions of sub-section (2); or (b) fails to comply with any order or requisition made under sub-section (1) shall, on conviction, be punished with fine which may extend to Rs. 10,000, and in the case of continuing contravention or non-compliance with further fine which may extend to Rs. 100 for every day after the first during which such contravention or non-compliance continues.
Chapter XII Chapter XII
189. Building for human habitation not to be used as Godown, etc., and vice versa
Building for human habitation not to be used as Godown, etc., and vice versa. (1) No person shall without the written permission of the Chief Officer or otherwise than in conformity with the terms of such permission,— (i) use or permit to be used any building or part thereof originally constructed or authorised to be used for human habitation as a godown, warehouse, workshop, workplace, factory, stable or a motor garage; or (ii) use or permit to be used for human habitation any part of a building not originally constructed or authorised to be used for that purpose. (2) if any person contravenes any provision of sub-section (1), he shall, on conviction, be punished with fine which may extend to Rs. 10,000, and in the case of continuing contravention with further fine which may extend to Rs. 100 for every day after the first during which such contravention continues.
Chapter XII Chapter XII
190. Removal of buildings, structures, etc., which are in ruins or likely to fall
Removal of buildings, structures, etc., which are in ruins or likely to fall. (1) If it shall at any time appear to the Chief Officer that any building or other structure or anything affixed to such building or structure is in a ruinous condition or likely to fall, or in any way dangerous to any person occupying, resorting to or passing by such building or structure or any other structure or place in the neighbourhood thereof, the Chief Officer may, by written notice, require the owner or occupier of such building or structure to pull down, secure, remove or repair such building, structure or thing or do one or more such things and to prevent all causes of danger therefrom. (2) The Chief Officer may also, if he thinks fit, require the said owner or occupier, by the said notice, either forthwith or before proceeding to pull down, secure, remove or repair the said building, structure or thing, to set up a proper and sufficient hoard or fence for the protection of passers by and other persons. (3) If it appears to the Chief Officer that the danger from a building, structure or thing which is ruinous or about to fall is of hourly imminence, he shall, before giving notice as aforesaid or before the period of notice expires, fence of, take down, secure or repair the said structure or take such steps or cause such work to be executed as may be required to arrest the danger. (4) Any expenses incurred by the Chief Officer under sub-section (3) shall be paid by the owner or occupier of the structure and shall be recoverable in the same manner as an amount due on account of a property tax.
Chapter XII Chapter XII
191. Penalty for defacing building, etc.
Penalty for defacing building, etc. Any person— (a) who, without the consent of the owner or occupier, and in the case of municipal property without the permission in writing of the Chief Officer, affixes any posting bill, placard or other paper or means of advertisement against or upon any building, wall, board, fence, pale, post, lamp-post or the like; or (b) who, without such consent or permission, as aforesaid, writes upon, soils, defaces or marks any such building, wall, board, fence, pale, post, lamp-post or the like, with chalk or paint or in any other way whatsoever, shall, on conviction, be punished with fine which may extend to fifty rupees.
Chapter XII Chapter XII
192. Fixing of lamps, brackets, etc., to houses
Fixing of lamps, brackets, etc., to houses. The Chief Officer may erect or fix to the outside of any building brackets for lamps to be lighted with oil, or gas, or subject to the provisions of the Indian Electricity Act, 1910, for lamps to be lighted with electricity or otherwise, or subject to the provision of the Indian Telegraph Act, 1885, for telegraph wires or telephone wires or wires for the conduct of electricity for locomotive purposes. Such brackets shall be erected or fixed so as not to occasion any inconvenience or nuisance to the occupants of the said building or of any others in the neighbourhood, or to the public.
Chapter XII Chapter XII
193. Regulation of huts
Regulation of huts. It shall not be lawful for any person to erect any hut or range or block of huts of to add any hut to any range or block of huts already existing on the appointed day, without giving previous notice to the Chief Officer. The Chief Officer may require such huts to be built so that they stand in regular lines, with a free passage or way in front of and between every two lines, of such width as the Chief Officer may think proper for ventilation and to facilitate scavenging, and at such a level as will admit of sufficient drainage; and may require such huts to be provided with such number of privies and such means of drainage as he may deem necessary. If any hut or range or block be built without such notice being given to the Chief Officer, or otherwise than as required by the Chief Officer, the Chief Officer may give written notice to the owner or building thereof, or to the owner or occupier of the land on which the same is erected or is being erected, requiring him within such reasonable time as shall be specified in the notice to take down and remove the same, or to make such alterations therein or additions thereto as having regard to sanitary considerations the Chief Officer may think fit.
Chapter XII Chapter XII
194. Improvement of huts
Improvement of huts. (1) Where the Council is of opinion that any hut, whether used as a dwelling or for any other purpose, and whether existing on the appointed day or subsequently erected, is by reason— (a) of insufficient ventilation or of the manner in which such hut is crowded together with other huts; or (b) of the want of a plinth or of a sufficient plinth or of sufficient drainage; or (c) of the impracticability of scavenging, attended with risk of disease to the inhabitants of the neighbourhood, the Council shall cause a notice to be affixed to some conspicuous part of such hut, requiring the owner or occupier thereof, or the owner of the land on which such hut is built, within such reasonable time as may be fixed by the Council in this behalf, to take down and remove such hut or to carry out such alteration or works as the Council may deem necessary for the avoidance of such risk. (2) Where any such owner or occupier refuses or neglects to take down and remove such hut or to carry out such alterations or works within the time appointed, the Chief Officer may cause such hut to be taken down, or such alterations or works to be carried out, in accordance with the requirements of the Council. (3) Where such hut is taken down by the Chief Officer, he shall cause the materials of the hut to be sold, if such sale can be effected; and the proceeds, after deducting all expenses, shall be paid to the owner of the hut, or if the owner is unknown or the title disputed, shall be held in deposit by the Council until the person interested therein shall obtain an order of a competent Court for the payment of the same: Provided that, where any such hut, which had not been constructed in contravention of any law for the time being in force at the time of such construction, is taken down and removed under this section, compensation shall further be paid to the owner or owners thereof and the amount thereof, in case of dispute, shall be ascertained and determined in the manner provided in section 315.